San Bernardino County Employees Retirement Association
File #: 19-1064    Name:
Type: Receive and File
File created: 8/24/2020 In control: BOARD OF RETIREMENT
On agenda: 9/3/2020 Final action:
Title: Receive and file the summary of change orders for August 2020 on tenant improvements project at 348 W. Hospitality Lane.
Attachments: 1. Exhibit A: PCCO 007, 2. Exhibit B: PCCO 008
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

 

FROM:                                            Joe Michael, Chief Information Officer

 

SUBJECT:                                           Summary of Change Orders on Tenant Improvements Project at 348 W. Hospitality Lane

 

RECOMMENDATION:

title

Receive and file the summary of change orders for August 2020 on tenant improvements project at 348 W. Hospitality Lane.

body

 

BACKGROUND:

On September 5, 2019, the Board approved proposed contracts for tenant improvements at 348 W. Hospitality Lane.  As part of that approval, the Board granted the Chief Executive Officer (CEO) authority to sign change orders up to $5,000, and granted joint authority of the Board Chair and the CEO to approve change orders that exceed $5,000.  A monthly report will be provided to the Board during the pendency of the project.

 

In August 2020, a change order was executed for time extension due to Covid-19 and change order delays. The change order extends the project completion date to October 6, 2020, with no change to the contract sum.

 

Additionally, a change order for patch and paintwork in the Board Room with a total contract sum change of $1,227.05 was executed. The contract time is not affected by this change order. 

 

BUDGET IMPACT:

None.

 

STRATEGIC PLANNING GOAL/OBJECTIVE:

Quality Employer and Workplace

 

STAFF CONTACT:

Joe Michael

 

ATTACHMENTS:

Exhibit A:                     PCCO 007

Exhibit B:                     PCCO 008